Fluorite Ridge Mine Safeguard Project

The Fluorite Ridge Mine Safeguard Project was located on private and public land approximately 12 miles northeast of Deming in Luna County, New Mexico. The project involved safeguarding 18 shafts, four adits, 16 open stopes and two trenches.

The contractor was the Lopez Excavating of Penasco, NM.

Year Completed: 1999
Cost: $144,385.51
Project Engineer: John Kretzmann, P.E.
Project Manager: Raymond Rodarte