Sugarite Gob Reclamation Project - Phase VIII/Yankee-Vukonich Maintenance II

Summary and Photographs

The Sugarite Gob Reclamation Project – Phase VIII is located about six miles northeast of Raton in Colfax County, New Mexico. The project area (see Sheet 1 of 3) is on unplatted public and private land within the Maxwell Land Grant.

The Yankee-Vukonich Maintenance II Project is located about eight miles northeast of Raton in Colfax County, New Mexico. The project area (see Figure 7) is on public and private land within Section 30, T 32 N, R 25 E and Section 36, T 32 N, R 24 E, NMPM.

The focus of these joint projects is to provide remedial reclamation to better control erosion and sedimentation at previously reclaimed gob (coal mine waste) piles in Sugarite Canyon State Park and in Yankee Canyon. These joint projects include the following work:


• Construction of straw bale terraces, coir roll terraces, sediment barrier dams, and coir bag gully packing and application of hydro-slurry at Gob Sites A1, A3, A4, A5 and A8 at Sugarite.
• Construction of a rough bed rock channel with coir rolls at Gob Site D in Yankee Canyon.
• Gob fire extinguishment, full soil treatment and application of hydro-slurry at Gob Site D in Yankee Canyon.
• Planting of seedlings at Gob Sites A1, A2S, A3, A4, A5 and A8 at Sugarite and at Gob Site D at Yankee Canyon, including planting hole amendments, seedling protection tubes where required, and maintenance and protection of plantings for six months.
• Grading required for access to the sites along designated access roads and trails and closure of these roads and trails as specified by ripping, amending where indicated, and reconstructing and installing waterbars.
• Hydroseeding using an extended-term flexible growth medium and broadcast seeding at designated areas and areas disturbed by construction.

The Contractor shall leave project areas in as good or better condition than before disturbance.

The Engineer's Estimate for this project is $516,800.

You may link to the all Specifications and Maps below.

Sugarite Gob Reclamation Project - Phase VIII/Yankee-Vukonich Maintenance II:  Contract and Specifications
Figures and maps:
Figure #1 Figure #2 Figure #3
Figure #4 Figure #5 Figure #6
Figure #7 Figure #8  
Sheet #1 Sheet #2 Sheet #3

 

Images of the Project
   
Gob Piles A4 and A1 - August 2011
Gob Pile A3 - August 2011
   
Gob Pile A5 - May 2011

Gob Pile A8 - July 2012

   
Coir Blocks at Gob Pile A2S - July 2012
   
Yankee-Vukonich Gob Pile D - September 2012
 

Low Bidder's List:
814 Solutions LLC - $429,297.08
Duran-Bokich Enterprises - $644,276.00

NON-MANDATORY PRE-BID CONFERENCE
Friday, May 24, 2013 at 10:30 a.m.
Attendance List

   

 

 

NOTE: Administrative questions and/or comments contact: John Kretzmann @ 505.476.3423 or e-mail
Technical questions and/or comments contact: John Kretzmann @ 505.476.3423 or e-mail

 
Year Completed:
Cost: $
Project Engineer
: John Kretzmann, P.E.
Project Manager: Zoe Isaacson